A subcontractor called me: “Hey Pim, that’s all well and good, you and your BIM. But what exactly is that one truth? Is it the BIM model, the technical specifications, the color and materials schedule, or the specifications?”
I knew right away what he was talking about. “Oh shit. This is about The Pulse.”
“That’s right—how do you know that?”
“Because that’s the only project where we use specifications. And I have some bad news right off the bat: those specifications are the governing contract document here.”
“But that’s impossible, man!”
“Why not?”
“Because the materials listed in it don’t appear in the project at all!”
Sometimes it’s awful to be proven right.
A year and a half earlier, I had warned about exactly this risk. At VORM, we normally work without specifications but with a technical description. The BIM model is our source of truth. At The Pulse, however, they opted for specifications anyway.
VORM Bouw handled the technical development following the final design and the environmental permit. This included the specifications and the accompanying drawings and models. These documents were thoroughly reviewed and discussed before they became the basis for further development and implementation.
And yet, things went wrong.
This is my objection to the current system: we design a building digitally, extract information from the model, store it in a flat specifications document, and supplement it separately. And then, in the event of contradictions, that flat document has the final say. So you end up with a source of truth and a document that determines when that truth doesn’t apply. Nice and clear.
Of course, technical specifications are necessary for information that isn’t sufficiently evident from the model. Agreements regarding delivery, performance, and standards must also be documented somewhere. But why do we also create a separate document that can override the model?
This has another unfortunate consequence. The specifications keep project leaders and managers out of the model. After all, the information is also contained in a familiar document. Why would they need to learn how to read a model?
Because that model shows what we’re going to build. It shows where materials belong and how components fit together. So give those people training: work planners, project managers, and their supervisors. Teach them to find information, ask questions, and evaluate changes. After all, we can’t keep digitizing things to the point where the manager has to look over our shoulders, can we? And then print out the progress for him.
As far as I’m concerned, the specifications—as a separate, guiding document alongside the BIM model—are hopelessly outdated. Anyone who agrees on a single source of truth must ensure their contract documents align with it. Otherwise, we’ll keep arguing about which document takes precedence.
And the one who has to build outside the plan ends up paying the price.